How to Calculate Underground STP Capacity for a Building?
As residential and commercial buildings grow, so does the volume of wastewater they produce. An underground Sewage Treatment Plant (STP) treats this wastewater without taking up valuable above-ground space. But it only works well if it is sized correctly. An undersized plant struggles to meet discharge norms and breaks down under peak load. An oversized plant raises installation and running costs, and can perform poorly because of low loading. This guide explains how to arrive at a sound STP capacity, from occupancy and water use to peak flow, design margin and tank volume.
Step 1: Estimate Occupancy
Occupancy drives everything that follows. Design for the population the building is intended to serve, not just the number of people on day one.
. Residential buildings
Use the design occupancy of the project, not the current number of residents. Apartment complexes often fill up gradually, but the STP has to cope once every unit is occupied. For example, a block of 100 flats with four occupants each has a design population of 400. Many local authorities assume a higher figure per dwelling, so confirm the norm that applies to your project.
. Commercial and mixed-use buildings
Offices, malls, hotels and restaurants have two kinds of users: regular occupants (staff, residents) and visitors. Both must be counted, and their water use differs. Occupancy can also swing sharply through the day, so estimate the most probable daily load rather than a single headcount.
Step 2: Estimate Daily Water Use
Water use is calculated on a per-capita basis, expressed in litres per capita per day (LPCD). For residential buildings in India, 135 LPCD is the commonly used design figure under the National Building Code (NBC), of which roughly 45 LPCD is for flushing. Always check the figure permitted by your local authority and the latest edition of the code.
Daily water use = Number of occupants × LPCD
For 400 occupants at 135 LPCD: 400 × 135 = 54,000 litres per day.
Other building types use water very differently. The table below gives indicative values only; confirm exact figures against the NBC and local bylaws before finalising a design.
| Building Type | Indicative Basis | Approx. Water Use |
|---|---|---|
| Residential | Per person | 135 litres per day |
| Office | Per person | 45 litres per day |
| Day School | Per student | 45 litres per day |
| Hotel (Up to 3-Star) | Per bed | 180 litres per day |
| Restaurant | Per seat | 70 litres per day |
Mixed-use projects should be calculated block by block (for example residential tower, retail podium and clubhouse) and then added together. Amenities such as swimming pools, gyms and cafeterias should be assessed separately.
Step 3: Convert Water Use to Wastewater
Not all water supplied to a building ends up in the sewer. Some is lost to gardening, cleaning, evaporation and similar uses. Design practice in India generally assumes that about 80% of supplied water becomes wastewater, in line with the CPHEEO Manual on Sewerage and Sewage Treatment Systems. Local pollution control board or municipal guidelines may specify a different factor, so check this first.
Daily wastewater = Daily water use × 0.80
Worked example
| Step | Calculation | Result |
|---|---|---|
| Design occupancy | 100 flats × 4 persons | 400 persons |
| Daily water use | 400 × 135 litres | 54,000 L/day |
| Daily wastewater | 54,000 × 0.80 | 43,200 L/day |
| In kilolitres | 43,200 ÷ 1,000 | 43.2 KLD |
This 43.2 KLD figure is the average daily flow. It is the starting point for sizing, not the final plant capacity.
Step 4: Apply Peak Flow and Design Margin
Buildings do not produce wastewater evenly through the day. Flow peaks in the morning and evening in residential buildings, and during working hours in offices. Two adjustments turn the average flow into a practical STP capacity.
. Peak flow
Peak flow is the average flow multiplied by a peak factor, commonly in the range of 2 to 3 for small buildings. In the example above, 43.2 KLD spread over 24 hours is about 1.8 m³/hour. With a peak factor of 3, the peak is about 5.4 m³/hour. Peak flow mainly governs the sizing of sewer lines, the collection sump and pumps. Most STPs include an equalisation tank so that the biological treatment stage receives a steadier flow.
. Design margin and standard size
A margin of 10% to 20% is usually added for future occupancy, higher-than-expected use and operating flexibility. The result is then rounded up to the nearest standard plant size.
| Step | Calculation | Result |
|---|---|---|
| Average daily flow | From Step 3 | 43.2 KLD |
| Add 15% design margin | 43.2 × 1.15 | ≈ 49.7 KLD |
| Nearest standard size | Round up | 50 KLD STP |
The margin should be a conscious decision, not a habit. If the building will fill in phases, a modular design lets the plant grow with the load instead of running oversized for years.
Step 5: Capacity Is Not the Same as Tank Volume
STP capacity (KLD) tells you how much wastewater the plant can treat in a day. It does not tell you how large the tanks are. Tank volume depends on how long wastewater must stay in each treatment stage, known as the hydraulic retention time (HRT), and on the strength of the wastewater (its BOD and COD load).
As a rough illustration only, a 50 KLD plant with a total retention time of about 20 hours across the equalisation, biological, settling and disinfection stages would need roughly 42 m³ of working volume (50 × 20 ÷ 24). Actual volumes come from the process design and depend on the technology chosen, so they should always be confirmed by the plant designer.
For a closer look at how each unit in a plant is designed and what it does, see this guide to STP design and the function of each piece of equipment.
Step 6: Plan the Underground Space
Because the plant sits below ground, the civil and site conditions matter as much as the process design. Before finalising layout and capacity, assess the following:
. Available basement or underground footprint, including depth and clear height.
. Soil conditions and groundwater level, which affect excavation, waterproofing and buoyancy.
. Structural loading, especially if vehicles or buildings will sit above th tank.
. Access for desludging, equipment removal and routine maintenance.
. Ventilation and odour control for enclosed spaces.
. Inlet and outlet levels, so that flow reaches and leaves the plant without excessive pumping.
Step 7: Choose the Treatment Technology
The two technologies most often used in compact underground installations are MBBR (Moving Bed Biofilm Reactor) and MBR (Membrane Bioreactor). They differ in space requirement, output quality, cost and maintenance.
| Factor | MBBR | MBR |
|---|---|---|
| How it works | Biofilm grows on floating media in the aeration tank, followed by a settling stage | Biological treatment combined with membrane filtration in place of settling |
| Space needed | Moderate | Smaller footprint |
| Treated water quality | Good; usually needs tertiary filtration for reuse | Very high; suited to demanding reuse |
| Cost | Lower capital and operating cost | Higher capital cost and membrane replacement |
| Operation | Robust, tolerant of load variation | Needs careful membrane cleaning and monitoring |
The right choice depends on the available space, the quality of treated water required and the operating budget. When tight space or high reuse quality is the priority, MBR often makes sense. When simplicity and lower cost matter more, MBBR is a common choice.
Step 8: Check Discharge Norms and Reuse Plans
Treated water must meet the standards set by the Central Pollution Control Board (CPCB), the state pollution control board and any local authority, depending on where it is discharged or reused. Standards can differ by state and by use. Decide early how the treated water will be used (flushing, gardening, cooling or discharge), because the reuse plan affects both the treatment technology and the capacity you need.
Common Mistakes to Avoid
. Sizing for today's occupancy only. This leaves no room for the building to reach full capacity.
. Skipping peak flow. Average flow alone can lead to undersized pumps and sumps.
. Ignoring non-resident load. Visitors, staff and amenities add to the total.
. Confusing capacity with tank volume. The two are related but calculated differently.
. Over-sizing for safety. Excess capacity raises costs and can hurt treatment performance at low load.
. Overlooking site constraints. Groundwater, access and structural limits can change the design.
Frequently Asked Questions (FAQs)
Q1. What STP capacity do I need for a 100-flat apartment complex?
As a worked example, 100 flats with four occupants each, at 135 LPCD and 80% wastewater generation, produce about 43.2 KLD. After adding a design margin, a 50 KLD STP is typically suitable. Your actual figure depends on local occupancy norms and water use.
Q2. Is STP capacity the same as the size of the tank?
No. Capacity is the volume treated per day. Tank volume depends on retention time and wastewater strength.
Q3. Why is 80% used for wastewater generation?
It reflects the fact that part of the supplied water is not discharged to the sewer. It is the figure generally used in Indian design practice, but local guidelines may differ.
Q4. Should I design the STP for future occupancy?
Yes. Designing only for initial occupancy often forces costly upgrades later. A phased or modular design is a good option for projects that fill up gradually.
Conclusion
Sizing a STP starts with a simple calculation: occupancy × water use × 80%. But a reliable design goes further. It accounts for peak flow, a sensible design margin, retention time, available underground space, the treatment technology and the discharge or reuse requirement. Getting these right protects your investment, keeps the plant compliant and supports reuse of treated water.